Sink

I met with Gary Livsey from the Union on 25/10 and he responded very enthusiastically to the request for a sink, although he pointed out that work could not start in the immediate future.
I asked for an update on 01/12 and received the response:
"I have not managed to sort out arrangements but will look to install early in the new year."

Thomas Miles Sun 11 Dec 2016 6:38PM
I did not dwell too much on the health and safety issues because I feared the Coop being shut down there and then for breach of food hygiene rules!
Ai Van K Sun 11 Dec 2016 11:32PM
wow, congrats for taking the initiative and getting somewhere with the sink!

Thomas Miles Sun 30 Apr 2017 10:39AM
The delay to the long-awaited sink if frustrating, which I can only imagine due to the fact that the major works have priority and are ongoing.
I have sent the following message to Gary Livsey:
"As we approach the end of this academic year, could we get an update on how the installation of the sink will fit into the timetable of works underway?"
Andrea Vidal Durà · Sun 11 Dec 2016 6:14PM
If we see that we don´t have an answer soon we can try to push a little bit using Health&Safety reasons to request the sink. Maybe we can also talk to our Activities Officer in the Union (as a society we have one... it used to be Kay Morrison but no idea if she is still) :smiley: